For Colorado, and all, Prevailing Wage public works projects, Davis Bacon general determinations have no pre-determined increases – meaning that the prevailing wages are good for the life of the project.
However, special determinations can be requested by the awarding body on a per-project basis! These special determinations will be specific to your particular Davis-Bacon job, and could contain pre-determined increases. In the event that a special determination request is made, the process could take up to 90 days to complete. The contracting agency or awarding body will provide the contractors with these special determinations.